Phil Crannell

PORTS & MARITIME GROUP INTERNATIONAL

Ports & Maritime Projects

Europe

CSMART architecture by PDR Architects-Amsterdam


CSMART

Center for Simulator and Maritime Training

Almere, The Netherlands



Client – Carnival Corporation

November- 2012 - 2014

Budget – Client Confidential


Responsibilities – Project Management – Programing and REQ/RFP Phase services for a Design Build development program


New facility on greenfield 2.8 hectare site to house 4 full mission bridge simulators and 4 engine room simulators

Engaged by Carnival Corporation’s Project Development leadership to prepare program of requirements intergrading academic specifications into single document for use in budgeting and eventual RFQ and RFP steps. Upon completion of the programing phase assisted in evaluation of site options resulting in selection of greenfield 2.8 hectare site.


Advised on selection of Dutch PM. Oversaw RFQ and RFP phases. Advised Carnival on selection of most qualified DB team and assisted in negotiations with best-qualified DB team. Upon selection monitored completion of architectural and engineer design. Assignment continued to provide construction phase services.




CSMART

Center for Simulator and Maritime Training

Almere, The Netherlands


Client – Carnival Corporation

November- 2014 - ongoing

Budget – Client Confidential


Responsibilities – Master Project Management – Construction Phase services

The new LEED Gold certified CSMART facility will house navigational and engine room simulators in various configurations from classroom stations up to part-task and full mission solutions, interlinked to provide training and assessment for the entire ship’s crew. CSMART’s new simulation complex will be three times larger than the existing facility.


Services were broad spectrum and included monitoring and advising client and construction team members during the permitting, site preparation and construction phase of the CSMART 11,000 sm + facility. Participated in review and selection of marine simulator systems and related projection and display suppliers for integration into facilities bridge and engine room simulator programs.




CSMART  Hotel

Center for Simulator and Maritime Training

Almere, The Netherlands


Client – Carnival Corporation

November- 2014 - ongoing

Budget – Client Confidential


Responsibilities – Project Management – Programing, conceptual design and REQ/RFP Phase services for a Design Engineer development program


New hotel with 176 rooms on Greenfield site.


Carnival required a purpose built hotel to be located immediately next to the CSMART facility to accommodate attendees while attending weeklong training programs in the new simulator and training complex. 


PMG was retained to lead the programing phase and conceptual design of the hotel followed by coordinating selection of a Dutch PM to manage the RFQ/RFP process to select an Engineer Build team to develop the hotel.  In order to present a unified training center complex appearance the hotel’s conceptual design included similar architectural elements and finishes used in the new CSMART.  To allow any weather movement between hotel and training center, the hotel design includes a below grade walkaway connecting the hotel lobby and parking to CSMART.


Operational and budget opportunities captured in the hotel design allowed for all training center and hotel parking to be located on 2 levels below the hotel, instead of two separate parking structures. As a result opens space was increased and CSMART construction cost reduced.




CSMART  Hotel

Center for Simulator and Maritime Training

Almere, The Netherlands


Client – Carnival Corporation

November- 2014 - ongoing

Budget – Client Confidential


Responsibilities – Master Project Management – Construction Phase services

New hotel with 176 rooms on Greenfield site.


Managed the engineer build team’s completion construction and permitting documents. Providing ongoing construction phase services monitoring services advising client on project status and opportunities to manage completion schedule and budget.


Advised client during pre-qualification and selection of hotel consultants to assist in optimizing the design.  Also advised client on selection of hotel management company to operate the hotel once completed. 